The permanent easement includes rights of access to perform the functions and uses of the easement by the District. The temporary construction easement would only be for the initial construction of the project with an expiration date or time period and not extend to ongoing maintenance and use. Access to the easement area would be...

Weeds within the maintenance easement that may impact flood safety and/or required environmental plantings associated with the project will be controlled by and at the expense of the District. For example, if weeds are physically blocking District staff’s ability to assess the integrity of the levee system they may be pulled. Another example is if...

Structures are not allowed within the easement area except common boundary fencing. Landscaping would be allowed so long as it doesn’t interfere with the District’s improvements and maintenance thereof.

The District will pay the property owner to have improvements modified, removed, moved or replaced depending on the situation. Certain improvements are more portable than others such as hot tubs, small garden sheds, greenhouses, gazebos in many cases can be moved out of the easement area. Permanent improvements such as decks, gazebos with foundations, concrete...

Non-conforming structures would be handled in a similar manner as conforming except that the District and County take no responsibility to ensure that a non-conforming structure is brought into conformance as a result of the project.

See Landscaping, no permanent structures allowed within permanent easement area.

Attorney fees are not reimbursable. If at the time the District enters into negotiations any of the conditions outlined below in the Code of Civil Procedure 1263.025 are met, the homeowner could get their own appraisal and the District would reimburse reasonable costs up to $5,000. (a) A public entity shall offer to pay the...

If the project receives CEQA approval and funding and the Board of Supervisors decides to authorize implementing construction of the project then the District may elect to use its powers of Eminent Domain as established in the US Constitution, Federal code, State code, and Water Code Appendix 68-5.13 to acquire the necessary easement for the...

The property owner would not be liable for construction or actions of the District related to the easement and its improvement constructed therein.

The District will become liable for incidents that occur within its easement during and after construction of the project with certain exceptions where the property owner or third party were negligent or purposely caused the incident.

The District has no permanent right to perform maintenance so acquiring a permanent easement will make the District responsible for the permissions and uses granted by the Easement Deed and carry the associated liability.

The survey work is being done by a licensed surveyor. Matt Vander Dussen works for GHD. In 2019 Matt conducted a topographic survey of the project area using a combination of Drone LiDAR, photogrammetry, and traditional survey methods. One deliverable from this work was a digital shapefile of the levee/TRB centerline. In 2020 this work...

This is not the method used to determine the spatial relationships, their locations were surveyed independently as described above, but having everything in digital format allows these areas and distances to be measured.

It has been difficult to describe the temporary easements (TCE’s) in a generalized way because they will be negotiated and delineated based on the available space within backyards and side yards. This will be better understood after the appraisal meetings with homeowners in which potential work areas and impediment are identified. The District needs to...

No. Trees or structures that can be worked around can remain within the TCE’s. The goal will be to disturb as little as possible during construction.

TCE’s may include driveways or side yards to connect the work area to Vendola Drive for equipment and material access purposes. These temporary access areas might be located every 5 or so houses depending on the location along the project and ease of access to the levee. The access needs will be identified and negotiated...