San Anselmo Flood Risk Reduction Project update, November 2020
The first part of the Sunnyside Detention Basin construction was completed ahead of schedule in mid-November. Work included demolition of all the existing buildings and structures, stripping and stockpiling gravel and topsoil to be re-used at the site, and excavation and off-haul of approximately 20,000 cubic yards of earth. The site was covered with mulch … Continued